3. Risk management

Determining risk

Question 1/3
Whilst you are preparing your risk treatment plan, you identify that there are exposed live parts located where you need to perform electrical work. Which of the following should always be attempted first?
(Refer to part 2.4 Risk management: The 5 step process of the Electrical Safety Code of Practice 2010 – Risk Management (the Code))

Risk treatment measures

Question 2/3
You have now determined that the exposed live parts cannot be isolated. Which step of the five step risk management process contained in the Electrical Safety Codes of Practice 2010 – Risk Management should you do next?
(Refer to part 2.4 Risk management: The 5 step process of the Code)

Monitoring risk

Question 3/3
After implementing your risk treatment plan, why should you monitor and review the measures?
(Refer to part 2.4 Risk management: The 5 step process of the Code)